TABLE OF CONTENTS                                                                                                                      Page

 

 


List of Table

Table 2.1

Selection of Preferred Option for KET Station

Table 2.2

Major ground level works areas / works sites for railway works

Table 2.3

Tentative Construction Works Schedule of the Project (Condensed Schedule)

Table 3.1

Construction Noise Criteria for Activity other than Percussive Piling

Table 3.2

Acceptable Noise Level for Fixed Plant Noise

Table 3.3

Representative Noise Sensitive Receivers

Table 3.4

Key Noise Sources to the Existing NSRs

Table 3.5

Summary of Fixed Plant Noise Sources for the proposed WIL

Table 3.6

Existing Buildings to be Demolished

Table 3.7

Summary of Key Construction Works along the WIL

Table 3.8

Unmitigated Construction Noise Levels during Non-restricted Hours

Table 3.9

Maximum Sound Power Level (SWL) for Key Fixed Plant

Table 3.10

Quieter PME Recommended for Adoption during Construction Phase

Table 3.11

Noise Mitigation Measures for Certain PME during Construction Phase 

Table 3.12

Summary of Mitigated Construction Noise Levels during Non-restricted Hours

Table 3.13

Predicted Residual Impacts Due to the Proposed Project

Table 3.14

NSRs Eligible for the Provision of ITR

Table 4.1

Construction Ground-borne Noise Criteria

Table 4.2

Operational Ground-borne Noise Criteria

Table 4.3a

Identified NSRs for Assessment of Ground-borne Construction Noise Impacts due to TBM operation

Table 4.3b

Identified NSRs for Assessment of Ground-borne Construction Noise Impacts due to Construction Works at Open Works Areas

Table 4.3c

Identified NSRs for Assessment of Ground-borne Construction Noise Impacts due to the Construction of Adits

Table 4.4

Operational Ground-borne Noise Sensitive Receivers

Table 4.5

Wave Propagation Properties of Soil

Table 4.6

Loss factor for Coupling into Building Foundation

Table 4.7

Predicted Overall A-weighted Noise Level for Tunnel Boring

Table 4.8a

Predicted Construction Ground-borne Noise Impact Associated with the PME Use at Open Works Areas

Table 4.8b

Predicted Construction Ground-borne Noise Impact Associated with the PME Use for Construction of Adits

Table 4.9

Summary of Operational Ground-Borne Noise Impact Assessment (without mitigation measure)

Table 4.10

Summary of Operational Ground-Borne Noise Impact Assessment (with mitigation measure)

Table 5.1

Matrix for Impact Significance Threshold Before Mitigation: Relationship between Sensitivity to Change and Magnitude of Change

Table 5.2

Affected Area (m2) in Construction and Operation Phase

Table 5.3

Significance of landscape impacts in the construction and operation Phases

Table 5.4

Proposed Landscape and Visual mitigation measures in Construction Phase

Table 5.5

Proposed Landscape and Visual mitigation measures in Operation Phase

Table 5.6

Significance of Visual Impacts in the Construction and Operational Phases

Table 6.1

Potential Indirect Impact on Built Heritage Sites during Construction Phase

Table 6.2

Potential Indirect Visual Impact on Cultural Heritage Sites during Operational Phase

Table 6.3

Potential Indirect Vibration Impact on Cultural Heritage Sites during Operational Phase

Table 7.1

Summary of C&D Material Volumes

Table 7.2

Summary of Frequency of Barge Movements and Routings

Table 7.3

Summary of Waste Handling Procedures and Disposal Routes

Table 8.1

Reviewed Historical Aerial Photographs

Table 8.2

Potential Contaminative Land Uses within or in vicinity of the Study Area (KET Section)

Table 8.3

Potential Contaminative Land Uses within or in vicinity of the Study Area (UNI Section)

Table 8.4

Potential Contaminative Land Uses within or in vicinity of the Study Area (SYP Section)

Table 9.1

Summary of Water Quality Objectives for Victoria Harbour WCZ

Table 9.2

Summary of Water Quality Objectives for Western Buffer WCZ

Table 9.3

Summary Statistics of Marine Water Quality in the Victoria Harbour WCZ and Western Buffer WCZ in 2006

Table 9.4

Maximum Waste Water Quantities during Construction Phase

Table 11.1

Hong Kong Air Quality Objectives

Table 11.2

EPD Air Quality Monitoring Data at Central/Western Station in 2005 & 2006

Table 11.3

Representative Air Sensitive Receivers in the vicinity of Kennedy Town Station Work Sites during Construction Phase

Table 11.4

Representative Air Sensitive Receivers in the vicinity of University Station Work Site during Construction Phase

Table 11.5

Representative Air Sensitive Receivers in the vicinity of Sai Ying Pun Station Work Site during Construction Phase

Table 11.6

Rock Crushing Plant – Dust Emission Design Control Measures

Table 11.7

Temporary Stockpiles – Dust Emission Design Control Measures

Table 11.8

Barging Facilities – Dust Emission Design Control Measures

Table 11.9

Emission Factors for Dusty Construction Activities at Kennedy Town Abattoir Site

Table 11.10

Emission Factors for Dusty Construction Activities at Kennedy Town Station Site

Table 11.11

Emission Factors for Dusty Construction Activities at Western PCWA

Table 11.12

Predicted Cumulative Hourly Average TSP Concentrations at Representative Air Sensitive Receivers 

Table 11.13

Predicted Cumulative 24-Hour Average TSP Concentrations at Representative Air Sensitive Receivers 

Table 13.1

Summary of Key Environmental Outcomes / Benefits

Table 14.1

Project Implementation Schedule for All Works Areas

Table 14.2

Implementation Schedule Specific for Works Area MA - Underground Magazine Site

Table 14.3

Implementation Schedule Specific for Works Area B – Kennedy Town Abattoir and Incinerator Area